Building progress
Updated each quarter with the same numbers we file on MahaRERA, and a photo from the same corner of the site.

Where it stands
- March 2026Excavation and foundationsDone. The banyan's roots were mapped first and the basement moved two metres to miss them.
- September 2026Frame to the fifth floorDone.
- NowSixth floor slab and terraceDue end of December 2026.
- 2027Walls, plumbing, electricalFloor by floor from the ground up.
- 2028Finishes, courtyard, liftsThen the occupancy certificate.
- December 2028PossessionAs registered.
Quarterly progressExample, invented numbers
| Work | Planned | Done |
|---|---|---|
| Excavation | 100% | 100% |
| Foundations and basement | 100% | 100% |
| RCC frame | 85% | 82% |
| Masonry | 10% | 6% |
| Plumbing and electrical | 0% | 0% |
Filed for the quarter to September 2026. The frame is three points behind because of a wet August; the plan absorbs it.

Visit the site
- When
- Saturday and Sunday, 10 to 5. Weekdays by appointment.
- Where
- Off Baner Road, behind the Mahalunge bus stop, Pune
- Sample home
- A fitted two-bedroom on the ground floor
- Phone
- +91 20 0000 0129
Wear flat shoes. You'll get a hard hat at the gate.